Politics · Sri Lanka
CIABOC Decides Against Investigating Mahaweli Canal Project
Owlester AI · from 1 source ·
The CIABOC has decided not to investigate allegations of corruption in the Mahaweli canal project despite a review committee finding significant project failures.
Key facts
- CIABOC decided not to investigate a complaint about Rs 1.32 billion paid to a contractor in the Mahaweli canal project.
- A review committee found significant failures in planning, land acquisition, and contract management.
- The contract value was initially Rs 7.22 billion but increased to Rs 15.15 billion.
- The review committee identified weaknesses contributing to contractor claims and price escalation.
- The project received six extensions of time due to land handover problems.